Question : (TCO 1) A problem-solving technique that reassembles a system’s component pieces into a complete, new, and improved system is

  • systems design.
  • systems analysis.
  • cause-and-effect analysis.
  • joint application design (JAD).
  • None of the above

Question 2. Question : (TCO 1) A system proposal may be presented as a

  • report.
  • verbal presentation.
  • walkthrough.
  • All of the above
  • None of the above

Question 3. Question : (TCO 1) A committee of executive business and system managers that studies and prioritizes competing project proposals to determine which projects will return the most for an organization and should therefore be approved is a

  • joint application committee.
  • joint requirements committee.
  • steering body.
  • prototyping body.
  • None of the above

Question 4. Question : (TCO 1) Which of the following is not a category of constraints?

  • Schedule
  • Technology
  • Priority
  • Cost
  • Policy

Question 5. Question : (TCO 1) A description of activities and services that a system must provide is a

  • nonfunctional requirement.
  • functional requirement.
  • prototype.
  • physical requirement.
  • None of the above

Question 6. Question : (TCO 3) Which of the following is the amount of delay that can be tolerated by a noncritical task without causing a delay in the completion date of the entire project?

  • Optimistic duration
  • Pessimistic duration
  • Critical path
  • Slack time
  • None of the above

Question 7. Question : (TCO 3) Which of the following is NOT shown on a PERT chart?

  • Scheduled start date
  • Actual start date
  • Task name
  • Estimated duration
  • Intertask dependencies

Question 8. Question : (TCO 3) A tool for helping management understand the dynamics and impact of changing project parameters, such as cost, schedule, scope, and quality, is

  • total quality management.
  • project management.
  • joint project planning.
  • expectations management matrix.
  • None of the above

Question 9. Question : (TCO 3) Which of the following establishes a project start date and then schedules forward from that date?

  • End scheduling
  • Remote scheduling
  • Forward scheduling
  • Reverse scheduling
  • None of the above

Question 10. Question : (TCO 3) Which of the following establishes a project deadline and then schedules backward from that date?

  • End scheduling
  • Remote scheduling
  • Reverse scheduling
  • Forward scheduling
  • None of the above